Post-Implementation review
Subsequent to the Commissioning of a GBAS installation and after an appropriate period of operation States/ANSPs should consider conducting a Post Implementation Review.
- It should provide assurance that the residual safety risks associated with the operation of the GBAS continue to be managed to acceptable level.
- It should ensure that lessons learnt from the initial operating period are captured.
- It should be able to identify any issues experienced and remedial action to address those issues.
- It should ensure that any outstanding tasks for activities within the Safety Case have been appropriately addressed.
- It should validate that assumptions are still applicable.
The Post Implementation Review should involve the review of:
- Service Requirements and whether the GBAS has met those Service Requirements.
- Operational practices for the GBAS.
- Implementation process and areas for improvement.
- Hazards associated with the operation of the GBAS and whether existing risk assessments remain valid.
- Any occurences or system related issues.
- Any safety related issues.
- Whether the safety benefits envisaged from the implementation of the GBAS have been met.