Post-Implementation review

Subsequent to the Commissioning of a GBAS installation and after an appropriate period of operation States/ANSPs should consider conducting a Post Implementation Review.   

  • It should provide assurance that the residual safety risks associated with the operation of the GBAS continue to be managed to acceptable level.
  • It should ensure that lessons learnt from the initial operating period are captured.
  • It should be able to identify any issues experienced and remedial action to address those issues.
  • It should ensure that any outstanding tasks for activities within the Safety Case have been appropriately addressed.
  • It should validate that assumptions are still applicable.

The Post Implementation Review should involve the review of:

  • Service Requirements and whether the GBAS has met those Service Requirements.
  • Operational practices for the GBAS.
  • Implementation process and areas for improvement.
  • Hazards associated with the operation of the GBAS and whether existing risk assessments remain valid.
  • Any occurences or system related issues.
  • Any safety related issues.
  • Whether the safety benefits envisaged from the implementation of the GBAS have been met.